Planning Commission Minutes - 03/04/2025 (Joint Workshop)MINUTES
JOINT WORKSHOP MEETING — MONTICELLO PLANNING
COMMISSION & CITY COUNCIL
Tuesday, March 4, 2025 — 4:45 p.m.
Mississippi Room, Monticello Community Center
Commissioners Present: Andrew Tapper, Teri Lehner, Melissa Robeck, Rick Kothenbeutel,
Teri Lehner
Councilmembers Present: Mayor Lloyd Hilgart, Charlotte Gabler, Lee Martie, Kip
Christianson
Councilmembers Absent: Tracy Hinz
Staff Present: Angela Schumann, Steve Grittman, Jim Thares, Tyler Bevier,
Matt Leonard, Bob Ferguson, Anne Mueller
1. Call to Order
Andrew Tapper called the joint workshop of the Monticello Planning Commission and
City Council to order at 4:46 p.m.
Angela Schumann addressed Commission and Council, noting a quorum by each was in
attendance for discussion purposes of a Concept Plan review. Angela Schumann stated
that a concept review is not a formal zoning or land use application nor public hearing,
but instead a workshop for both governing bodies to provide feedback for the concept
proposer prior to formal application submission. Comments by the Commission and
Council are encouraged for discussion. Regarding timeline for the concept review,
Angela Schumann stated that notices were not published but were mailed out to the
neighboring parcels within 350' of the subject property. Because this is not a public
hearing, questions and comments made will be considered if time allows and minutes
documented for summary of the outcome.
Jim Thares, Economic Development Manager, arrived at 4:52 p.m.
2. Joint Workshop Agenda
A. Concept Stage Submittal for a 106.05 acre development including data center
uses, within a Light Industrial Park, Mixed Neighborhood, Commercial and
Residential Flex and Estate Residential land use designation areas as identified by
the Monticello 2040 Vision + Plan.
City Planner Steve Grittman displayed the concept proposal, stating the proposal
would require an amendment to the City's land use plan Future Land Use Map.
The concept property totals approximately 106 acres over four parcels within the
Monticello Orderly Annexation Area (MOAA), abutting City property to the north
and east. Planner Grittman stated that the applicants propose to reguide the
property to appropriately designate land use to support development of a data
center project of up to 1.3 million square feet. Planner Grittman explained that the
City Council recently amended its 2040 Comprehensive Plan to accommodate the
Planning Commission Workshop Minutes — 03/04/2025
potential for Data Center development in the Light Industrial Park (LIP) land use
category. Approximately 30 of the 106 acres of the proposed site is currently
designated for LIP land use. The other 76 acres are guided by the Monticello 2040
Plan for residential or residential/commercial mixed uses and are otherwise
surrounded by both rural residential and parkland.
Planner Grittman stated that at this level of the concept review, the main objectives
are to give feedback to the proposer with City guidance from a land use
perspective, so as to inform how they proceed with application, and to outline
issues for mitigation and other objectives. The outcome of this meeting is not for
approval or denial, but for conceptual consideration for land use and site plan
design.
Planner Grittman spoke to the mixed land use designations, including mixed
neighborhood (MN), commercial and residential flex (CRF), and estate residential
(ER) in proximity of the LIP designation. The surrounding parcels are designated
rural residential of varying acreage within the township and would remain as such
per 2040 plan, as is currently used.
Planner Grittman explained the subject parcel includes electric transmission
infrastructure stretching from 90t" Street North to the Xcel Energy substation and
beyond.
When reviewing a proposed change in land use, Planner Grittman stated that the
goal is to discuss how to consider the proposal on the site and best meet goals of
protecting or buffering surrounding uses. Different buffering practices and means
may be utilized in a LIP specifically for data centers, over those for a more general
industrial use. Noise generation is a common concern with data centers,
particularly when generators are tested.
Planner Grittman spoke of the parcels along 901" Street North, stating that their
guidance as primarily mixed neighborhood residential and commercial and
residential flex land uses make them less sensitive to location than other land use
categories. In this case, there is also an Estate Residential (ER) parcel at the
northwest portion of the proposed site. Land use in Estate Residential is written to
prescribe for larger suburban lots, typically with a % acre range per lot and as a
means for providing higher value/larger lot availability within the City. Adjacency to
the Bertram Chain of Lakes Park lends opportunity for higher -amenities and access
to natural resources for this type of housing. A decision point is whether it is
possible to maintain some estate residential in this area relative to a data center
use. In this scenario, the potential applicant is looking to convert the entire site into
Light Industrial Park LIP.
Planner Grittman stated that the City's standpoint if this were to be considered,
would be to ensure the Estate Residential would be relocated to another
appropriate site to maintain the long-term land use plan for accommodation of this
type of housing. He indicated that as the City continues to grow and annexation
Planning Commission Workshop Minutes — 03/04/2025
boundaries expand over time and area, all land uses should be taken into
consideration for compatibility.
Planner Grittman spoke of the need for buffering for industrial uses and to the
uniqueness that comes with data centers in terms of impact to municipal utilities,
including the potential for heavier use of water supplies, especially if used for
building cooling. The City would monitor demand for water and wastewater.
Utilities are in place along 901" Street North, but a viability study would need to take
place to evaluate the ability to meet additional long-term utility needs.
Melissa Robeck asked Steve Grittman what amenities are located in this area of the
Bertram Chain of Lakes. Angela Schumann stated that along the east side of
Bertram, the current amenities include passive recreational trails and mountain
biking trails.
Councilmember Charlotte Gabler asked for clarity if the parcel abuts Bertram to the
west. Steve Grittman confirmed yes and, per aerial depiction, is heavily wooded.
Andrew Tapper sought confirmation on the location of the Estate Residential
parcel. Angela Schumann clarified the Estate Residential area is surrounded on the
north and west sections by Bertram.
Mayor Lloyd Hilgart stated that the park was a $26 million acquisition and the City
invested in more industrial land to the north and northeast which includes an
electrical transmission corridor. He stated while land surrounded by Bertram is
desirable for residential, high power lines and industrial land to the east may make
it less desirable. Lloyd Hilgart asked of the likelihood for residential homes
considering these factors. He also inquired if the site would be access off of 90tn
Street North.
Planner Grittman explained that an extension of Dalton Avenue would serve as an
industrial route through to 901" Street North.
Lloyd Hilgart pointed out that the road would lead through the industrial park for
others to get home. He noted that the City is in short supply of estate residential
land, but with the underground utilities and overhead electrical line corridor that
runs through this area, the viability of executive homes are a point to discuss.
Charlotte Gabler asked if noise generation might affect wildlife, with concern for
sound and vibrations.
Angela Schumann stated that an environmental study would be required for
development square footage of a larger size, such as the proposed.
Charlotte Gabler then asked if the depicted footprint size is set and suggested that
the larger scale is too big to be next to the park. By designing smaller buildings, they
could pull back and away from the park's property line and closer to the other
industrial buildings.
Erik Anderson, representative for Scannell Properties, indicated that the purpose of
3
Planning Commission Workshop Minutes — 03/04/2025
the concept is for discussion.
Andrew Tapper noted the portion of land left undeveloped at the northeast corner
of the proposed site plan, which is suggested as Monticello EDC land expansion
area. Andrew Tapper stated that from his perspective, he doesn't see the demand
to build homes next to a data center. Mr. Tapper asked the potential applicant to
present.
Erik Anderson, Senior Development Associate for Scannell Properties, introduced
himself and gave an overview on the data centers they have developed in the
greater Twin Cities area and how the subject parcels were specially selected
because of the industrial nature for potential use. Ideally, he stated that the desire
is to build off the existing electrical infrastructure and work with the land that is
already carved out for industrial use. The benefit of the high -power utility lines is in
their favor to meet their extensive electrical supply demands, requiring minimal
additions for transmission means over a barren site.
Erik Anderson stated that after researching the Midwest and Minnesota, the
subject parcel was selected as ideal land and location for building a data center. Mr,
Anderson noted the displayed site plan, stating the required setbacks from and
under the existing power lines in the middle of the site made for the most efficient
configuration possible. The City's requirement would entail a connection from
Dalton Avenue through to 901" Street North, providing full access to and around the
buildings. The excess land shown as industrial economic development land,
depicted and mentioned by Mr. Tapper, may or may not be used in the concept
plan and Scannell is willing to work with the City to reguide to Light Industrial Park
(LIP) while maintaining buffer areas. Mr. Anderson thanked Council and the
Commission for their time to review the presentation and welcomed questions for
conversation and feedback.
Lloyd Hilgart asked how tall the proposed buildings will be.
Erik Anderson stated approximately 28 to 32 feet tall.
Andrew Tapper asked about the amount of power required.
Erik Anderson replied that a power study with Xcel Energy is currently underway
and the results have not yet come back. Currently, 150 megawatts exists to serve
the site; the other buildings would use slightly less.
Lloyd Hilgart asked about the frequency of use of backup generators, or when
tested and for how long they might idle.
Erik Anderson replied that these factors are also related to the power study
underway with Xcel Energy, as demand at this standpoint is still unknown.
Mayor Hilgart stated the height of buildings was not egregious, and that the
proposed use would not generate much traffic flowing through and not many
employees; the proposal presented does not make it a "bad neighbor". The
exception and question is when the generators kick on and produce noise. Mr.
Planning Commission Workshop Minutes — 03/04/2025
Hilgert suggested the possibility of a tour of another site which has generators to
anticipate the volume and how often generators are actively running, as the noise
generation seems to be the biggest unknown issue and he would like to learn more.
He noted that the primary question is whether this land is a prime location for
estate residential, and stated that the west is more likely the case than the east.
Planner Grittman made note regarding the generator issue; the proposed site plan
shows 100 generators, or more. The unknowns are if they will operate sequentially
or if only one or two run at once, or if half of them run all at once, factoring the
difference it could generate.
Rick Kothenbeutel asked of landscaping at the west and south portions of the
proposed, if planned for a berm or another noise barrier, much like freeways, and if
that might be incorporated.
Councilmember Kip Christianson asked what tenant intent is considered and
whether the facility be operated by the potential applicant or will it be sold or
leased out.
Erik Anderson stated this was a good question. It is not commonplace to have
speculative data centers and they are currently working with a few potential
tenants and are willing to work with the City to find the most ideal occupant. Due
to the significant investment into each building, the holding period is expected to
be twenty -plus years.
Kip Christianson asked if the potential applicants are prepared for the City's plan to
extend Dalton Avenue and asked of security or setback measures to be
implemented in having a public right-of-way running through the complex. Berms
and fences may be utilized to obstruct visibility and were suggested.
Erik Anderson stated this was a good point. The facilities do need to remain secure
and fencing or gated access would be installed to separate it from the public right-
of-way. Regarding the powerlines, Mr. Anderson reexplained that there are three
high powerlines and a gas line underground, depicted by the four lines noted on the
site plan running north/south.
Kip Christianson asked the developer to confirm whether the terrain is hilly and
how grading might be impacted for larger buildings.
Erik Anderson stated that the site is generally flat with a gentle slope and they
conceptually plan to build up to berm along the west and south sides of the site as
means to buffer the area.
Kip Christianson asked how the tenants might work with the City for utility
infrastructure funding. Water usage and waste load is still unknown; utility studies
will take place with the City to meet tenant demand, said Mr. Anderson.
Andrew Tapper asked City Engineer Matt Leonard about the utilities in this portion
of the annexation area.
5
Planning Commission Workshop Minutes — 03/04/2025
Mr. Leonard indicated that no utilities currently exist on 90t" Street North, but they
do on Dalton Avenue. Utilities would need to be brought up to 90t" Street as well
and depending on the demand for water. A revised analysis for industrial growth
and comprehensive plan land use growth would be conducted once a user is
determined. The current utility study was conducted based on current land use
planning and the current utility models utilized by the City. By knowing who the
user will be and if utilizing water for cooling methods, an understanding on the
impacts for demand can be prepared.
Kip Christianson asked if the land had yet been purchased.
Erik Anderson stated that a contract is in place to purchase the land with a
timeframe to allow for a workable amended comprehensive plan based on what
the City allows.
Lloyd Hilgart stated the biggest concern is use of the land and whether Council and
Commission think the westerly land could be used for something other than
houses. He stated that the use itself, light or regular industrial, would likely be less
egregious than, say, a trucking company, with active vehicles coming and going.
Again, he noted that the feedback should be whether the land in question should
be retained for housing. If no, then the matter is for the best means to berm and
screen and how much to allot for setbacks, and where to replace the housing.
Andrew Tapper stated that Bertram Chain of Lakes Park is the most desirable
aspect of the area. The question is whether a 40-acre farm field adjacent could be
converted into a use other than for farming. The overhead powerlines are an issue.
Lloyd Hilgart stated how the infrastructure and streets are laid out is also important
and concurred with the powerline consideration.
Erik Anderson spoke of the potential future land use and noted that he understood
the importance of estate residential (ER). With the comprehensive plan
amendment, they would be to also work with the City to identify a location to
relocate the designated 40 acres. Of the total 1,102 acres designated ER, the
proposal would displace only 3.7% from the ER district.
Kip Christianson spoke of the displayed aerial image, remarking that the majority of
the ER district is located along the eastern edge of the Township. Mr. Christianson
noted other areas of Estate Residential in the future land use plan. the ER districts
also designated on the Silver Creek Township side of the city near the golf course
and asked of the small area on the south side. Ms. Schumann confirmed this as
Haven Ridge West. Mr. Christianson noted an LIP section of land available along 194.
the City recently revised its land use plan to allow for data centers in the Light
Industrial Park and asked of Mr. Anderson's thoughts on pursuing a Light Industrial
Park parcel like this already appropriately zoned (guided).
Erik Anderson stated this parcel had been considered and the parcel owner was
approached only to discover the topography to be too hilly and is encompassed in
Planning Commission Workshop Minutes — 03/04/2025
wetlands. This portion is outside of the Monticello Orderly Annexation Area and
utilities are much further away. Because of these factors, the location is less than
ideal. Considering the powerline corridor already in existence, additional load and
substations can be factored for the proposed site.
Councilmember Rob Stark agreed that the powerlines and resources seem to be the
right fit for the proposal's consideration in lieu of development alternatives.
Lloyd Hilgart felt that the use does not impact Bertram. The buildings proposed are
not too tall and should not create considerable noise pollution. The use would not
bring additional traffic to this passive area which may perhaps impact the
surrounding existing homes, but should not impact Bertram. Land exists for
housing, but great land is in short supply for greater amenity housing.
Charlotte Gabler mentioned the proposed Meadowbrook residential development,
with various housing options, as a recent conversation at Council. She suggested
additional conversation is needed regarding Estate Residential. By taking away from
the designated zone and moving to another could be less desirable in terms of the
landscaping and aesthetics than this land by Bertram.
Councilmember Teri Lehner said regarding the housing standpoint, if Council and
Commission should say no, there is no guarantee of future developers of that level
vying for the Estate Residential property. She stated that she is undecided, as this
location is a prime asset, but the future development prediction is uncertain.
Councilmember Lee Martie did not see how the site was deemed prime real estate,
with Bertram in the backyard and industrial park in the front. If building a million
dollar home, why chance the type of development around the neighborhood?
Teri Lehner agreed with Mr. Martie and expanded, the determination of this being
prime or not is all in how a developer can work with the land and its complexities to
build executive homes.
Lee Martie added that speculation could be infinite if waiting on the right
developer, rather than sitting vacant as has been.
Kip Christianson comparably spoke of the powerline corridor in Big Lake along the
river as similar and how the land was delineated to work with the existing high
powerlines; it is hard to escape infrastructure set in place and there is a need to
work around and under them.
Andrew Tapper added that he resides near high-powerlines and does not actively
hear them; it is something he has gotten used to. Mr. Tapper inquired as to how
many lots on average could be constructed on the 40 acres.
Lloyd Hilgart stated 80 city residential lots would be the maximum.
Angela Schumann reminded Council and Commission of the streets and utilities
infrastructure that would factor into the acreage.
Planner Grittman displayed the concept plan, stating the three easterly buildings
7
Planning Commission Workshop Minutes — 03/04/2025
are approximately 800-900 feet from powerlines. If only two buildings were
proposed and laid out north/south, this would leave 500 feet of Estate Residential
land. He described road configuration options in creating lots.
Lee Martie referenced the other data centers depicted in the presentation which
did not appear to have any set in a blended residential setting and asked the
prospective applicant if the intent is for a blended proposal.
Erik Anderson said communications were had with a few residential developers
regarding building in the Estate Residential area. The biggest factor in building in
residential is establishing tree coverage in the development, as opposed to the
barren farmland that is less desired.
Andrew Tapper asked for a summary of the items discussed.
Angela Schumann summarized the main points of discussion. The number one item
for consideration, not for consensus or decision at this time, is whether the 40
acres will be retained for Estate Residential use, particularly considering the
presence of overhead powerlines. The boards discussed whether a data center can
be located on any portion of the easterly side of the proposed site and powerlines,
and if so, whether retaining any Estate Residential might still be useful. The group
did note that the Bertram Chain of Lakes Park is an asset, offering the ability of
Estate Residential development on the westerly boundary of the park. A question
regarding the size of buildings and their configuration on the parcel was also
considered. Some discussion was heard regarding generators, the noise and
frequency, and how it might be buffered by berms and landscaping walls, leading
into understanding utility infrastructure.
Lloyd Hilgart stated one data center to the east is not a huge deal - industrial is
industrial. Whether it is a data center or a warehouse should present no impact on
housing.
Mr. Hilgart opened the conversation to the general public.
One citizen asked if any existing data centers of similar size to the proposed exist in
Minnesota.
Erik Anderson stated that there are many proposed, but a 150 mega -watt data
center like the concept plans presented is not operational at this time. He
referenced larger proposals in Rosemount and Chaska.
Another citizen asked about the advantage of connecting Dalton Avenue and 90tn
Street North.
Angela Schumann explained the City's long-range transportation plan envisions
connectivity east -to -west through the City including the growth areas, west from
School Boulevard to 90t" Street and northward through the industrial park. She
noted that with this type of use, there would be consideration for separation of use
between residential and industrial, by means of landscaping and security concerns.
Planning Commission Workshop Minutes — 03/04/2025
Matt Leonard noted that at present, Dalton Avenue is a long dead end street, so
connectivity would help for emergency vehicle access and construction detour
alternatives. He noted that some cut-thru traffic might occur at the data center
using Dalton Avenue, but signage and other means to encourage alternative route
from Chelsea to 90th Street North could assist with traffic flow. As development
happens in this area, the City envisions upgrades to 90th Street North to include
shoulders and curb and gutter infrastructure, coinciding with the School Boulevard
expansion project.
Lloyd Hilgert recognizes the perspective of opening up Dalton Avenue and stated
that there could be an evaluation of how to access 90th Street without moving
through the industrial park.
A citizen commented that if landscaped setbacks and trees are considered for
buffering whether the powerlines would present an obstacle to that vegetation.
Erik Anderson replied that there may need to be discussion regarding an
encroachment agreement to provide landscaping and berming to buffer.
Lloyd Hilgart asked if any Council or Commissioners at current consensus were
vehemently opposed the consideration.
Angela Schumann noted that the proposer would be available following the
meeting for questions from members of the public afterward.
3. Adiournment
By consensus, the meeting was adjourned at 6:00 p.m.
Recorded By: Anne Mueller ="
Date Approved: May 6, 2025
ATTEST:
Angela SchVr�a)n, Comrhunity Development Director
E