City Council Resolution 2010-23CITY OF MONTICELLO
WRIGHT COUNTY, MINNESOTA
RESOLUTION NO. 2010-23
APPROVING FINAL PAYMENT AND ACCEPTING IMPROVEMENTS FOR
GRADING AND DRAINAGE IMPROVEMENTS AT THE
MONTICELLO MIDDLE SCHOOL AND A GLORIOUS CHURCH PONDS
CITY PROJECT NO.06CO09 (2006-09C)
WHEREAS, pursuant to a written contract with the City of Monticello awarded to Motzko
Companies, LLC of Delano, Minnesota, the contractor has substantially completed the work for
the grading and drainage improvements at the Monticello Middle School and A Glorious Church
ponds, including other appurtenant work in accordance with the contract;
WHEREAS, the final payment includes a deduction for items that were not completed by the
contractor, which include:
1) Repair of the bituminous pathway near the Monticello Middle School pond.
2) Ditch cleaning near A Glorious Church pond.
3) Erosion repair and pipe replacement at the east end of the Middle School pond.
NOW THEREFORE, BE IT RESOLVED BY THE CITY OF MONTICELL0, MINESOTA
that the work completed under said contract is hereby accepted and approved and that the Mayor
and City Clerk are hereby directed to issue a proper order for the final payment on such contract
subject to receipt of the following:
1) Satisfactory showing that the contractor has complied with the provisions of Minnesota
Statutes 290.92 requiring withholding state income tax (IC 134);
2) Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured (lien waivers);
3) Consent of Surety to Final Payment certification from the contractor's surety; and
4) Two year maintenance bond to start and extend two years from the date of acceptance of the
project by the City Council.
ADOPTED BY the Monticello City Council this 26th day of April, 2010.
CITY OF MONTICELLO
Clint Herbst, Mayor
ATTEST:
J Bill, City Administrator