City Council Resolution 2013-73CITY OF MONTICELLO
WRIGHT COUNTY, MINNESOTA
RESOLUTION NO. 2013-073
ACCEPTING IMPROVEMENTS AND APPROVING FINAL PAYMENT ON
2013 SEAL COATING AND FOG SEAL IMPROVEMENTS
CITY PROJECT ZZZSEAL
WHEREAS, pursuant to a written contract which the City of Monticello awarded to Allied Blacktop
of Maple Grove, Minnesota, the contractor has satisfactorily completed the work for the bituminous
sealcoating improvements for 2013 in accordance with the contract; and
WHEREAS, pursuant to an addendum to the contract with Allied Blacktop of Maple Grove,
Minnesota, which was approved by the Monticello City Council on August 26, 2013, the contractor
has satisfactorily completed the work for the fog seal improvements on Meadow Oak Avenue;
NOW THEREFORE, BE IT RESOLVED BY THE CITY OF MONTICELL0, MINNESOTA that
the work completed under said contract is hereby accepted and approved and that the Mayor and City
Clerk are hereby directed to issue a proper order for the final payment on such contract subject to
receipt of the following:
1) Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax;
2) Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured;
3) Consent of Surety to Final Payment certification from the contractor's surety; and
4) Two year maintenance bond to extend two years from the date of acceptance of the project by the
City Council.
ADOPTED BY the Monticello City Council, this 23rd day of September, 2013.
CITY OF MONTICELLO
Clint Herbst, Mayor
ATTEST:
k�x_� (�&,o