City Council Resolution 2008-93CITY OF MONTICELLO
RESOLUTION NO.2OW93
ACCEPTING IMPROVEMENTS 2007 STREET RECONSTRUCTION
CITY PROJECT NO.2007 -OIC
WHEREAS, pursuant to a written contract with the City of Monticello awarded to Northwest
Asphalts Inc. of Shakopee, Minnesota the contractor has satisfactorily completed the work for
reconstructing River Street from Craig Lane to CSAH 75, Craig Lane, Kenneth Lane, Hillcrest Road,
Hillcrest Circle, Hilltop Drive, Matthew and on River Street from CSAH 75 to the ball fields
including construction of curb and gutter, drainage and storm sewer improvements, sidewalk and
other appurtenant work in accordance with the contract;
NOW THEREFORE, BE IT RESOL VED BY THE CITY OF MONTrCELLO, MRVESOTA that
the work completed under said contract is hereby accepted and approved and that the Mayor and City
Clerk are hereby directed to issue a proper order for the final payment on such contract subject to
receipt of the following: 1) Satisfactory showing that the contractor has complied with the provisions
of Minnesota Statutes 290.92 requiring withholding state income tax; 2) Evidence in the form of an
affidavit that all claims against the contractor by reasons of the contract have been fully paid or
satisfactorily secured; 3) Consent of Surety to Final Payment certification from the contractor's
surety, and 4) Two year maintenance bond to extend two years from the date of acceptance of the
project by the City Council.
Adopted by the Monticello City Council this 24h day of November, 2008.
ATTEST:
C t Herbst, Mayor