City Council Resolution 2015-88CITY OF MONTICELLO
ACCEPTING IMPROVEMENTS AND APPROVING FINAL PAYMENT TO MUNICIPAL
BUILDERS INC. CITY PROJECT NO. 12CO03
WHEREAS, pursuant to a written contract with the City of Monticello, on May 28, 2013, Municipal
Builders, Inc. was awarded, by low bid, for the construction of the WWTF Sludge Dewatcring
Facility as part of the Phase I of the Wastewater Treatment Facility Biosolids Dewatering, Energy
Efficiency, Headworks and Site Improvements, City Project 12C003;
NOW THEREFORE, BE IT RESOLVED BY THE CITY OF MONTICELLO, MINNESOTA that
the work completed under said contract is hereby accepted and approved and that the Mayor and City
Clerk are hereby directed to issue a proper order for the final payment on such contract subject to
receipt of the following:
1) Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes
290.92 requiring withholding state income tax (IC 134);
2) Evidence in the form of an affidavit that all claims against the contractor by reasons of the
contract have been fully paid or satisfactorily secured (lien waivers);
3) Consent of Surety to Final Payment certification from the contractor's surety;
4) Two year maintenance which will be in effect from when the project was substantially complete
on December 31, 2013 until December 31, 2015.
5) Letter of acceptance from WSB for floor repair work.
ADOPTED BY the Monticello City Council this 14a' day of December, 2015.
ATTEST:
i
I .,
Jennifer Schreiber, CityClerk
CITY OF MONTICELLO
Brian Stumpf, Mayq