City Council Agenda Packet 11-17-1975AGENDA
SPECIAL MEETING OF THE MONTICELLO CITY COUNCIL
November 1 7, 1975 - 7:30 P. M.
Mayor: Con Johnson.
Councilmen: Denton Erickson, Dick Martie, Gene
Walters, Stanley Hall.
Meeting to be taped.
J1. Public Hearing - proposed assessment roll -
1975-1 Sanitary Sewer and Watcrmain Improve-
ment Project.
/2. Review of plans and specifications for new liquor
store.
✓3. Consideration of hockey rink.
/. Approval of minutes November G and November 10,
1975.
VS. Unfinished buesinces.
VU. New business.
✓ o►y�t
SNo�•/ 4.
MAI LI NG TO:
John Badalich
Mrs. Ruth Moore
Mike Holm
Don Smith
Ralph Block
k
ORR-SCHEIEN-MAYERON &ASSOCIATES. INC.
:.,,,,,,r7vlzJ fnurneere
November 17, 1975
Honorable Mayor & City Council
215 South Cedar Street
Monticello, Minnesota 55362
Re: Assessment Roll
Project 75-1
Gentlemen:
The following are the costs used in preparation of the assess-
ment rolls for the sewer and water improvement; Project Num-
bers 75TS-1, 75LS-1, 75TW-1, 75LW-1 and appurtenant work.
Final construction costs
5643,164.94 -
Engineering Design Fee (6-1/28)
41,805.72
Inspection and Survey Fees
35,159.46
City expenses paid
7,632.94
a Preparation of Assessment Roll (1B)
6,431.65
City Administration (3%)
19,294.95
Total Project Cost
$753,489.66
`Breakdown for final construction costs:
Original contract
$511,748.92
Chany,_- Order 01 N-. 66&1
47,186.04
ChanUQ Order #2 Nt'
11,195.05
Change Order 03 rj1.,17
57,718.61
Chanclo Order Nd (j,r�
8,548.53
Extra Work
6,767.59
Total
5643,164.94
Under direction of the City Council, we have combined all change
orders wi:_h the exception of Maple Street Project, Change Order
02, to the ruin project and determined a unit parcel assessment.
All oversizing of trunk mains, the Otter Creek culverts, and
509 of the street restoration was placed on ad valorem taxes.
It was resolved that the Monticello Apartments were to pay the
full project costs for Change Order Y2 excluding a unit parcel
assessment for Lot 5, Block P.
It was also resolved that Parcel 19585-A3 (Monticello 1st
Baptist Church) be asscsood as two units.
'hyr 1".i•,f 1l••... • m r .1l'Ur'rM Stdfr• 23$ , t•J73 r 1.
/7•x.1 �
Honorable mayor 6 City Council
City of Monticello —2- November 17, 1975
Re: Assessment Roll
Project 75-1
We further recommended that the River Terrace Trailer Court be
assessed as two units. This would be consistent with the pre-
vious policy of subdividing larger lots into approximately 100'
frontage for placement of sewer and water services. Based on
this criteria, the number of assessable units amounts to 157
units, excluding Change Order q2.
We have previously recommended placing a percentage of the
project costs on ad valorem taxes in respect to the frontage
of the cemetery and City Maintenance Building. by the same
policy of subdividing into 100' lots, the cemetery would have
contained 15 lots if residential, and the Maintenance Building,
4 lots. The assessable cost to this property or 19 units
amounts to $52,275.83 which is being placed on ad valorem taxes.
A breakdown of costs is as follows:
Total Costs of Project $753,489.66
Total costs to be placed on ad valorem taxes:
Water main oversizing $ 35,410.08
Sanitary sewer oversizinq 108,722.58
509 Street restoration
with appurtenants (otter Creek) 112,003.29
Cemetery and Maintenance Bldg. credit 52,275.83
5308,411.78
Total to be assessed excluding Maple Street Change Order: �f
$431,962.49 1
The City Council agreed to aosese 100% of street construction
of Sandy Lane to the 15 parcels in Creekside Terrace. The k
total net amount to be asocased is: ``
$471,962.49
502 Sandy Lane -3,117.00
Assessable amount.
$428,845.49
Therefore based on 157 unit parcols to be assessed, excluding
Maple Street, the per unit. assessment is:
$428,845.49 a $2,731.50/un.it
157
N
// 7.r A"/
Honorable Mayor s City Council
City of Monticello -3- November 17, 1975
Re: Assessment Roll
Project 75-1
Those 15 parcels on Sandy Lane will also have a per parcel
assessment including 100% street construction for a total asses-
ment of:
$2,731.50 + $3,117.00
15 = $2,939.30
The assessment for Change Order Number 2 will be as follows:
Total construction costs
Plus indirect costs
Project Cost
$11,195.05
1,920.34
$13,115.39
Parcel $20017, Lot 5, Block P, is to pay a unit assessment.
In addition Parcel 20010, Lot 1, Block 0, should be assessed
for the sewer and water stubs installed. This was previously
served by the city, but no stubs were ever brought up to the
property line. This stub assessment would be $405.15. The
Monticello Apartments would then be assessed as follows:
Project Costs $13,115.39
Unit Assessment (Parcel 020017) -2,731.50
Stub Assessment - 404.65
Amount Assessable to Apartment 5 9,979.24
At the City Council meeting, held November 10th, 1975, the
City Council agreed to defer this amount of $9,979.24 to the
Monticello Apartments, to the taxes payable in 1977.
Yours very truly,
ORR-SCII177LEN-KAYERON
-6 ASSOCIATES, INC.
ZXf��
John P. Badalich, P.E.
City Engineer
JPB/bsy
//-/7 )s d
J
n RESOLUTION ADOPTING ASSESSMENT R01.1.
ON 771E 1975-1 SANITARY SEWER AND WATERMAIN
IMPROVEMENT BONDS
BE 1T RESOLVED, that the City Counel1 of MonLi.-
cel.lo hereby adopts the attached assessment, roll on
the 1975-1 Sanitary Sewer and Watermain Improvement.
Bonds issued by the, City to finance the 1975-1
Sanitary Sewer and Watermain Improvement. Project..
BE IT FURTHER RESOLVED, that the City of Monti.-
celLo, pursuant to Minnesota Statutes, Section 429.061,
hereby orders Lite assessment shall be prorated over
twenty (20) years with equal installments of principal
with interest accrued at seven and one-half (71) per
cent per year to be paid annually.
Maor•
Citf'Administrator
Date Resolution Adopted: November 17, 1975.
I
G