Planning Commission Resolution 2014-020CITY OF MONTICELLO
WRIGHT COUNTY, MINNESOTA
PLANNING COMMISSION
RESOLUTION NO. 2014-020
Motion By: Burvee Seconded By: Heidemann
AMENDMENT TO THE MONTICELLO ZONING ORDINANCE, SECTION 5.2,
USE TABLE, AND 5.3, USE STANDARDS TO ALLOW TEMPORARY PUBLIC
INFRASTRUCTURE CONSTRUCTION FACILITIES BY INTERIM USE PERMIT;
AND APPROVING A REQUEST FOR AN INTERIM USE PERMIT FOR
TEMPORARY PUBLIC INFRASTRUCTURE CONSTRUCTION FACILITIES
WHEREAS, Shafer Contracting Co., Inc. has submitted an application for an ordinance
amendment and interim use permit to allow a contractor's yard as an interim use in the
Industrial and Business Campus (IBC) District, and
WHEREAS, the interim use of the proposed site for construction staging and concrete
mixing operations is in conjunction with an approved MnDOT roadway reconstruction
project of Interstate 94 between CSAH 39 and CSAH 18, and
WHEREAS, the Planning Commission held a public hearing on March 4, 2014 on the
application and the applicant and members of the public were provided the opportunity to
present information to the Planning Commission; and
WHEREAS, the Planning Commission has considered all of the comments and the staff
report, which are incorporated by reference into the resolution; and
WHEREAS, the Planning Commission of the City of Monticello makes the following
Findings of Fact in relation to the recommendation of approval:
1. The proposed ordinance amendment addresses needs arising from a changing
condition, trend, or fact affecting the subject property and surrounding area.
2. The proposed ordinance amendment will not create conditions that interfere with
achieving the goals and objectives outlined in the comprehensive plan.
3. The applicant will be required to comply with the conditions imposed as a basis for
approval of the interim use permit.
NOW, THEREFORE, BE IT RESOLVED, by the Planning Commission of the City of
Monticello, Minnesota recommends approval of an ordinance amendment to allow a
contractor's yard as an interim use in the Industrial and Business Campus District and
recommends that the processing of an interim use permit for the proposed contractor's yard
and portable concrete batch plant proceed upon approval of the ordinance amendment.
ADOPTED this 4th day of March, 2014, by the Planning Commission of the City of
Monticello, Minnesota.
MONTI7=;7zr N
By:
Fyle, Ch
ATTEST:
Angela S� 4 , Community Development Director
2