Planning Commission Resolution 2016-018CITY OF MONTICELLO
WRIGHT COUNTY, MINNNESOTA
PLANNING COMMISSION
RESOLUTION NO. PC- 2016 -018
RECOMENDING APPROVAL OF CONDITIONAL USE PERMITS FOR
BUILDING HEIGHT, CROSS PARKING AND ACCESS, AND FOR
BULK FUEL STORAGE IN AN I -1, LIGHT INDUSTRIAL DISTRICT
WHEREAS, the applicant has submitted a request to construct an addition to an
existing building; and
WHEREAS, the addition is designed to snatch the existing building and utilize
existing parking and circulation areas on the site; and
WHEREAS, the addition will require the approval of conditional use permits for
building height, cross - parking and access, and bulk fuel storage to facilitate the expansion of
the use as proposed; and
WHEREAS, the improvements are consistent with the intent and purpose of the I -1,
Light Industrial zoning district; and
WHEREAS, the improvements will not create any unanticipated changes to the
demand for public services on or around the site; and
WHEREAS, the stormwater and other impacts of the expansion are being addressed
through appropriate engineering review; and
WHEREAS, the Planning Commission held a public hearing on June 7t", 2016 on the
application and the applicant and members of the public were provided the opportunity to
present information to the Planning Commission; and
WHEREAS, the Planning Commission has considered all of the comments and the
staff report, which are incorporated by reference into the resolution; and
WHEREAS, the Planning Commission of the City of Monticello makes the following
Findings of Fact in relation to the recommendation of approval:
1. The proposed improvements are consistent with the intent and purpose of the I-
1, Light Industrial District.
2. The proposed improvements are consistent with the existing and future land
uses in the industrial park in which they are located.
3. The impacts of the expansion are those anticipated by industrial development
and are addressed through standard review and ordinances in place.
4. The building height, cross - parking and access, and bulk fuel facilities meet the
intent and requirements of the applicable zoning regulations.
CITY OF MONTICELLO
WRIGHT COUNTY, MINNNESOTA
PLANNING COMMISSION
RESOLUTION NO. PC- 2016 -018
NOW, THEREFORE, BE IT RESOLVED, by the Planning Commission of the City of
Monticello, Minnesota, that the Planning Commission hereby recommends that the
Monticello City Council approves the Conditional Use Permits for Building Height, Cross -
Parking and Access, and Bulk Fuel Storage, subject to the conditions listed in Exhibit Z as
follows:
1. Deferred Parking. The applicants provide a narrative on the number of parking
spaces that are needed for their business. The applicants have shown on the site plan
that the 52 spaces can easily be added if needed.
2. Cross parking and access agreement is applied and recorded against both parcels.
3. An encroachment agreement is executed should it be necessary to accommodate
storm water ponding design.
4. A development agreement is executed addressing all improvements to the site.
5. Curb Cut Width. The curb cut width shall be reviewed by the City Engineer.
6. The Landscaping Plan is modified to add or move plant materials that will enhance
the screening of the view of the loading docks from Dalton Way.
7. The requirements of the City Engineer are addressed per the Engineer's letter dated
June 1, 2016, and the applicants continue to work with the City regarding stormwater
management requirements.
8. Bulk fuel dispensing on the site shall only be for the fueling of company delivery
vehicles, and shall meet all other requirements of the applicable zoning ordinance,
along with required building and fire codes.
9. Any proposed signage changes shall be subject to the applicable sign ordinances and
a separate permitting process.
10. The requirements of other City staff are complied with.
ADOPTED this 7t' day of June, 2016 by the Planning Commission of the City of
Monticello, Minnesota.
MONTICELLO PLANNING COMMISSION
2
CITY OF MONTICELLO
WRIGHT COUNTY, MINNNESOTA
PLANNING COMMISSION
RESOLUTION NO. PC- 2016 -018
ATTEST:
Angela Schum of unity Development Director